Weymouth North Sea Wall
Client - Heidelberg Materials Contracting
Value - £705,000.00
Duration - 40 weeks
Profile Number - 23/53
Suttle Projects were instructed to refurbish the sea wall within Weymouth harbour. The scope of works entailed:
- Repointing works
- Concrete repairs
- Spray Concreting
We also cast a reinforced concrete upstand to the top of the wall, the purpose of this was to raise the flood defence level to maintain protection against a 1 in 100 year flood event.
Good value, high quality materials and service